The three replacement cabins at Camp Ashland Training Site were developed in response to major flooding and structural damage to the existing transient quarters. The project team provided structural and infrastructure design services to meet FEMA requirements, ADA accessibility standards, and applicable Federal Design Standards.

Despite being constructed during the COVID-19 shutdown, the cabins were completed on schedule and without contract cost increases, avoiding the material and labor escalation challenges common during that period.

2026

Ashland, Nebraska

4,700

$2,400,000